Laying of power cable 69 kv. dwg

Laying of Power Cable 69 KV.

Procedure: once the trench has been excavated, and if applicable to the respective land classified bed, cable is lowered into the trench, laying it done with a side boom 583 or a backhoe pc220lc - 8, which lifts the coil and moving it mobilizes and unwinding with sufficient experienced staff for this purpose who will control the advance of laying, the cable should fall by gravity effect, while a skilled (2) cable combed properly controlling non-overlapping; perform what hairstyle qualified for this purpose (electrical minimum b) who enzuncharan every 5 mts.